1. Wire delivery
Wire feeding equipment: Put the required processed wires on the intermediate wire feeding frame.
Required equipment: wire feeder, wire feeder.
Process requirements: Be careful not to scratch or scratch the surface of the wire. Avoid different wire tightness when multiple wires are processed at the same time
2. Cutting
Cutting line: use the cutting machine to cut the wire to the required length
Required equipment: computer wire cutting machine, multi-function wire cutting machine, wire cutting and stripping machine.
Process requirements: Do not cut the surface of the wire; Do not cut the copper wire; The error of the length of the peeling is not allowed to exceed +1mm.
3. Peeling
Wire stripping: According to the requirements of SOP, strip the insulation jacket of the corresponding length of the wire at the joint. Required equipment: Wire cutting and stripping machine, vertical stripping machine, pneumatic stripping machine Process requirements: Do not crush the surface; The error of stripping length is not allowed to exceed + 1mm.
4. Twisted wire
Twisted wires: Arranging and twisting the conductors at the joints
Required equipment: Cutting, stripping and twisting machine, cutting and twisting machine.
Process requirements: no scratching or scratching the surface of the wire; the copper wire must be twisted tightly, and loose wires are not allowed
5. Crimp terminal
Riveting terminal: Rivet the conductor at the joint and the plug terminal. Required equipment: terminal machine, single and double-head terminal machine, automatic terminal machine, copper strip machine, silent terminal machine. Process requirements: the terminal is not deformed and must meet the requirements of tension, riveting height and width
6. Dip tin
Tin dipping: tinning the joints to facilitate the insertion of circuit boards. Required equipment: automatic tin dipping machine, single and double-head tin dipping machine, cutting line tin dipping machine.
Process requirements: tinning is uniform, no loose wires are allowed, and the depth of tin dipping meets the requirements
7. Assembly: Assemble the plastic plug shell
Required equipment: electric screwdriver.
Process requirements: the screws are not allowed to expose the surface of the plastic shell; the torque required by the product must be met.
8. Conductivity test: use the instrument to conduct the continuity test of the wiring harness
Equipment needed: Continuity tester.
Process requirements: short circuit, open circuit, miswiring, poor contact, poor insulation and other phenomena are not allowed.
9. Packaging: Use plastic bags to package the finished wiring harness and put them in cartons
Required equipment: sealing machine and packing machine.
Technological requirements: the seal should be flat;